Circular No.01/2015/TT-BXD of Ministry of Construction

0
431
Ministry of Construction

This circular provides guidelines for determination of the unit labor cost in the management of the construction cost.

The unit labor cost is calculated according to the following formula:

GNC= LNCx HCBx 1/t

Where:

GNC: The unit labor cost paid to an employee who directly produces their output in a working day.

LNC : The input wage (including extra pays, mileage allowances, regional allowances, allowances for production stabilization failure, and taking into account market factors) used to calculate the unit labor cost  paid to an employee who directly produces their output in a working day.

HCB: The coefficient of the wage paid to an employee who directly produces the output.

t: 26 working days per a month.

In particular, wage inputs to determine the unit cost of construction labor is determined by region, from regions I to IV, respectively, 2.35 million / month; 2.15 million / month; 02 million / month and 1.9 million / month. Rank and salary ratio of direct labor manufacturing building is determined according to the 06 group of construction workers; directly engineers; artisans; a driver; diver; worker control boats, other equipment and ranged from 1.55 to 6.73